For Sale

Explore a variety of land options now selling at Bluestone, Mt Barker.

View Available Land

About

Bluestone’s carefully planned design boasts a balance of both convenience and open space, offering the hills lifestyle you’ve always wanted.

Discover Bluestone

Lifestyle

Bluestone is close to schools, shops, parks, and has it’s own range of outdoor activities

Explore the lifestyle

Updates

Stay up to date with new land releases, construction progress, and Bluestone community news.

Read the latest updates

Celebrating Bluestone’s Parkindula parkrun 2nd Birthday
Celebrating Bluestone’s Parkindula parkrun 2nd Birthday
Stage 7B – Fredrick Park
Stage 7B – Fredrick Park

Stage 7B – Fredrick Park

Home Stage 7B – Fredrick Park

Bluestone, Mt Barker Stage 7B – Fredrick Park

In Progress
Last Updated May 2025

Estimated Titles Available – End of May/1st week of June 2025*
Settlements Commencement – Refer to your sales contact and agent

*dates are estimates only and are subject to change 

Project Information

Completed

  • Bulk earthworks
  • Topsoil Strip
  • Lot Benching
  • Sewer Install
  • Stormwater
  • Water Main
  • CTS Works
  • Roadworks
  • Fredrick Park Reserve – Bulk Earthworks
  • Fredrick Park Reserve – Footpaths
  • Kerbs

In Progress

  • Retaining Walls
  • Footpath installation
  • Asphalt

Estimated Access for 7B

  • Valuations – Available now – for access please contact Customer Support
  • Soil Testing/Survey – After Practical Completion (estimated end of June unless appointment can be made available – please contact customer support)

Project Updates

May 2025 Project Update

May 2025 Project Update

As we near the completion of our construction programme, we’d like to provide an update on Stage 7B.

There has been a slight delay in road construction due to a change in the asphalt contractor. The originally engaged contractor ceased trading unexpectedly, and a new contractor had to be sourced at short notice. Asphalt works have now commenced however recent wet weather has temporarily impacted progress. Approximately two days of roadworks remain, and we now anticipate completion by early June, weather permitting.
 
Retaining walls and topsoil are ongoing and footpath installation is nearing completion. Based on current progress and subject to weather, we expect the roads to open to the public by the end of June.
 
Frederick Park Reserve Landscape works are scheduled to begin as soon as conditions allow, and we look forward to getting underway shortly.
 
Our next update will follow in June to notify of completion.

For any enquiries please contact our customer support at customersupport.sa@peet.com.au.

March 2025 Project Update

March 2025 Project Update

Aerial view from Wellington Road
Aerial view from Wellington Road
Aerial view from Wellington Road
Aerial view from Wellington Road
Aerial view from Wellington Road
Aerial view from Wellington Road
Aerial view from Wellington Road
Aerial view from Wellington Road

February saw significant progress in Stage 7B, with multiple milestones reached.

The retaining wall program is now over 50% complete, with works advancing through both Greenham and Harbury areas. Additionally, engineering access on Oaken is complete, enabling a large number of engineers to access the site.
Looking ahead, we will focus on completing the remaining roadworks and kerb installation throughout the remainder of the stage. The Common Service Trenches have also commenced and will continue into April. Asphalt installation is forecast to take place once these preparatory works are finished.
In April, we will be moving forward with access to the remaining portion of the site, following the completion of the roadworks. Builders will be notified as we approach this phase to ensure smooth coordination and access.
Exciting progress is also being made at Frederick Reserve, with footpaths nearing completion. Civil works are expected to be fully completed by the end of this month.
For any enquiries please contact our customer support at customersupport.sa@peet.com.au.

February 2025 Project Update

December 2024 Project Update

November 2024 Project Update

October 2024 Project Update

September 2024 Project Update