close
close

Bluestone Stage 7A - Frederick Park

 

Bluestone, Mt Barker Stage 7A - Frederick Park

IN PROGRESS

Last updated 10th April 2024

PROJECT INFORMATION

COMPLETED

  • Authority approvals
  • Sewer install
  • Bulk earthworks
  • Stormwater line
  • Watermain
 

IN PROGRESS 

  • Retaining walls
  • Roadworks
  • Kerbs
  • Common Services Trench
  • Basin works
  

ESTIMATED ACCESS FOR 

  • Valuations - Available now* Please contact customersupport.sa@peet.com.au for access details
  • Soil Testing - Early April 2024* 
  • Site Survey - Early April 2024*

 
ESTIMATED TITLES AVAILABLE 

May 2024*

SETTLEMENTS COMMENCEMENT 

From May 2024* (refer to your sales contract and sales agent)

*dates are estimates only and are subject to change 

 

April 10th 2024 Project Update

March saw a big push on road works with subbase rolled and kerbs commencing. By the end of this week machine kerbing will be completed, with handworks continuing on the finer details.

Retaining walls are continuing and as noted with the last update there has been some delay in the retaining program. We appreciate your patience whilst we continue works. The installation of the retaining walls is a complex process and we have been working closely with builders and engineers regarding availability for engineering access.

Common Services works have commenced- works will progress over April; footpath prep and pour to follow thereafter. We will be aiming for basecourse to be laid next week (pending weather) in readiness for asphalt to be down second half of April.

Please note, CST works will limit access for engineering on particular blocks so we will do our best to accommodate engineering access requests where reasonable.

Frederick Park works have commenced with the basin excavation taking shape. As we get into the final stages of construction, we also start to see wet weather. We anticipate Practical completion early June


Bulk Earthworks > completed
Stormwater Install > completed
Water Main Install > completed
Retaining Walls > 50% steel / 45% on sleepers
Roadworks > 100% subgrade / 100% subbase / 0% basecourse
Asphalt > second half of April
Kerb Installation > 95%
CST Works > in progress
Footpaths > commencing May
Basin Civil Works > commenced

March 19th 2024 Project Update

Stage 7A has made big progress in the past week with main services complete and road works well underway with the first run of kerbs down on Hassett Street.
Engineering access for Hassett blocks has now been pushed back to the start of April due to a slight delay with our retaining program. We are aiming to see the majority of retaining sleepers placed before Easter.
Kerbs are forecast to be completed by early April and asphalt down in the second half of April.

In even more exciting news, Frederick Park civils will commence in the next couple of months, so watch this space transform!

Bulk Earthworks > completed
Stormwater install > completed
Water main install > completed
Retaining walls in progress > 65% on drilling and posts / 35% on sleepers
Roadworks >50% subgrade / 30% subbase
Kerb installation >30%
CST works > commencing April
Footpaths > commencing May

March 2024 Project Update

Stage 7A is taking shape with Lot Benching completed. Reserve earthworks will start to commence next month.
Underground infrastructure are well underway with the last of the watermains to be completed this week, and CST crossings currently being completed. Common Services (Power, Gas, NBN) will commence next month.
Retaining walls are in progress, with the main focus being completing Hassett St to enable early engineering access for these blocks in the next couple weeks. The retaining crew are halfway through drilling for the stage and sleepers are being completed along Hassett St. Backfilling will commence within the next week.
Roadworks have also commenced following underground services with subgrade being laid on Hassett St in readiness for kerbs to commence at the end of the week. 

 

Bulk Earthworks > completed
Retaining walls in progress > 50% on drilling and posts / 25% on sleepers
Stormwater install > completed
Water main install > 95% completed
Roadworks > commenced
Kerb installation > commencing mid March
CST works > commencing April

February 2024 Project Update

Bulk earthworks are almost complete with the last of Linthorp St currently being benched.
Underground infrastructure is in progress; sewer main is complete, stormwater pits are mostly installed with the main line to follow. Water mains scheduled to commence in the coming weeks.
Retaining walls have recently commenced with Hassett St well underway.
Roadworks are scheduled to commence early March in preparation for the installation of kerbs.

 

Bulk Earthworks are nearly finished > 95% completed
Retaining walls in progress > 10% completed
Sewer main install > 100% completed
Stormwater install > 30% completed
Water main install > due to commence mid-Feb
Roadworks > due to commence late Feb/early March
Kerb installation > due to commence mid March

January 2024 Project Update

Bulk Earthworks are nearly finished > 80% completed
Retaining walls have commenced > 5% completed
Sewer install has begun > 30% completed
Stormwater to commence early next week

December 2023 Project Update

Bulk Earthworks are well underway with Hassett St blocks benched
Retaining walls have commenced
Sewer install are due to start soon

Get more with Bluestone Mt Barker

Subscribe to our updates to find out about new releases, special offers and events.

Please tell us some more about you. Your feedback will help us find the best option for you.

Please tell us some more about you. Your feedback will help us find the best option for you.

Step 1
Step 2
Step 3

Register now to download the Bluestone, Mt Barker Fast Facts.

View Bluestone, Mt Barker Fast Facts HERE

Please complete our short survey.
Your feedback will help us find the best option for you.

If you have signed up for updates previously, you can enter your email address here.

Don't have an account? Register now.

Subscribe to our updates, to find out about new releases, special offers and events.

Already have an account? Log in to Save and Compare.

View your Save and Compare

Continue browsing